abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb
Article

4 Aug 2020

Author:
Mighty Earth

Mighty Earth says funding of Matarbari coal plant contributes to excessive pollution, destruction of livelihoods for local community

"Ten Reasons Why Sumitomo's Matarbari Coal Plant is a Terrible Idea", 15 June 2019

...But despite Bangladesh’s commitment to using 100 percent renewable energy, the Japanese government and Sumitomo Corporation are proceeding with the construction of a new coal power plant in Matarbari, next to Bangladesh’s major coastal tourist area. Unbelievably, Japan’s government is considering whether to finance yet another coal plant in Matarbari...

The Matarbari coal plant units 1 & 2 will use unnecessarily polluting technology that would never be allowed in Japan, polluting up to 21 times the amount of SO2 and 10 times the amount of deadly particles than an average new coal plant in Japan...

The excessive pollution from the Matarbari coal plant units 1 & 2 would put nearby communities significantly over WHO health guidelines for concentrations of air pollution...

...[L]ocal media reported the cost of electricity from this plant is anticipated to be excessively high due to the construction delays, cost overruns and related coal infrastructure needed...

Matarbari Units 1 & 2 are under construction, with the Japanese government considering financing two more coal units. This is ironic, as Bangladesh is particularly vulnerable to the effects of climate change, especially sea level rise and flooding, and has joined countries in similar circumstances as part of the Climate Vulnerable Forum...

Bangladeshi news sources have reported that construction workers for Matarbari Units 1 & 2 went on strike after being forced to work during a national lockdown for COVID-19...

Japan’s participation in the Paris Agreement led the Cabinet to adopt a policy in 2019 to develop infrastructure which helps contribute to global reductions of CO2 emissions...

A survey of residents [who were displaced due to the construction of the first coal plant] found many were unable to take part in compensation programs, not provided with alternative employment, and left without their place of work or homes...

Air pollution and water pollution from these new coal plants threaten the long-term viability of Cox’s Bazar as a tourist destination and damage the potential for future economic development...