abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb
Article

17 Aug 2022

Author:
Max Avary & Paul Eckert, Radio Free Asia

Thailand: Court dismisses Mekong River activists’ case, rejects claims that buying power from Xayaburi Dam in Laos would cause damage

"Thai court dismisses Mekong River activists’ case against Xayaburi Dam in Laos", 17 August 2022

Thailand’s Supreme Administrative Court ruled in favor of the Electricity Generating Authority of Thailand’s controversial power purchase deal from a Lao dam on the Mekong River, ending a 10-year legal effort by river activists to halt the power deal over environmental and social concerns.

The court in Bangkok dismissed an appeal in a lawsuit launched in 2012 by the Thai Mekong People’s Network from Eight Provinces requesting the scrapping the agreement signed by the Electricity Generating Authority of Thailand (EGAT) to buy electricity from the Xayaburi Dam, Laos’ first Mekong River dam.

The members of the network argued that EGAT’s power purchase agreement (PPA) is causing significant damage to the livelihoods and environment of millions of Mekong River Basin residents. The case, which was dismissed by a lower court, argued that Thai agencies involved in the approval process had failed to follow proper procedures, including consultations with people affected by the dam.

The Thai Supreme Administrative Court rejected the concerns [...].

“The signing of the power purchase agreement with the Xayaburi Dam had no clear and direct impact on the environment and people,” the court said.

“In addition, the defendants had followed and conducted the proper procedures, the Procedures for Notification, Prior Consultation and Agreement (PNPCA),” it said.

“Therefore, the court sees that the defendants have done their jobs and proved that they were not negligent.”

[...]

Part of the following timelines

Court hears landmark case regarding impacts in Thailand of Laos' Xayaburi Dam

Xayaburi dam lawsuit (re Laos & Thailand)

Privacy information

This site uses cookies and other web storage technologies. You can set your privacy choices below. Changes will take effect immediately.

For more information on our use of web storage, please refer to our Data Usage and Cookies Policy

Strictly necessary storage

ON
OFF

Necessary storage enables core site functionality. This site cannot function without it, so it can only be disabled by changing settings in your browser.

Analytics cookie

ON
OFF

When you access our website we use Google Analytics to collect information on your visit. Accepting this cookie will allow us to understand more details about your journey, and improve how we surface information. All analytics information is anonymous and we do not use it to identify you. Google provides a Google Analytics opt-out add on for all popular browsers.

Promotional cookies

ON
OFF

We share news and updates on business and human rights through third party platforms, including social media and search engines. These cookies help us to understand the performance of these promotions.

Your privacy choices for this site

This site uses cookies and other web storage technologies to enhance your experience beyond necessary core functionality.