abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb

Cette page n’est pas disponible en Français et est affichée en English

Procès

1 Jan 2021

Bureau of Land Management lawsuit (re approval of Lithium Nevada's mine, USA)

Statut : CLOSED

Date de dépôt de la plainte
1 Jan 2021
Exactitude de la date
Année correcte
Non applicable
Communauté, Peuples indigènes, Défenseur des droits de l'homme, Individual
Lieu de dépôt de la plainte: États-Unis d'Amérique
Lieu de l'incident: États-Unis d'Amérique
Type de litige: National

Entreprises

Lithium Nevada (Part of Lithium Americas) Canada Exploitation minière
Bangchak Corporation Thaïlande Énergie renouvelable, Pétrole, gaz et charbon
Gangfeng Lithium Chine Ressources naturelles : Général, Exploitation minière

Against other:

Government

Sources

Snapshot Box

In early 2021 environmentalists, Native American tribes and a rancher filed a lawsuit to block Lithium Nevada’s construction of an open pit lithium mine in the Nevada desert to produce raw materials for electric vehicle batteries. They allege that the construction of the mine would negatively impact the local environment and cultural values of Native American tribes. In March 2023, the 9th Circuit Court of Appeals denied an emergency injunction filed in 2023, and the construction of the mine is now underway. 

Factual Background 

The desert area near the Nevada-Oregon border is home to the third largest known lithium deposit in the world. Lithium Nevada, a subsidiary of Lithium Americas, seeks to construct a 5,000-acre open-pit lithium mine to produce raw materials for electric vehicle batteries. Lithium Nevada claims that the mine could produce lithium for over 1.5 million electric vehicles per year for 40 years. Production from the mine is expected to begin by late 2026. The company has already invested over $150 million in the project.

Opponents to the mine (environmentalists, Native American tribes and a rancher) assert that it would harm the local environment and wildlife. Native American tribes claim the mine would harm sacred cultural values given its proximity to a site where dozens of Native people were killed in 1865. Opponents also argue Lithium Nevada is greenwashing the mining project by focusing on the mine’s contribution to renewable energy while disregarding the local environmental impacts. The company and federal government meanwhile argue that the mine is essential to quickly moving away from fossil fuels and investing in green energy, and that the emergency filings undermine efforts to fight climate change.

Legal Argument

Opponents of the mine argue that the Interior Department’s Bureau of Land Management illegally approved the mine’s construction plan without sufficient environmental review to expedite lithium extraction for renewable energy sources, namely electric car batteries. They also argue the project violates environmental laws.

Native American tribes have joined the lawsuit, stating that the Bureau of Land Management approved the mine without their free, prior, and informed consent, violating their rights to religion, culture, and ancestral lands. Multiple tribes have ties to Thacker Pass, and they argue the site contains the remains of their ancestors and should not be disturbed.

Legal Proceedings 

In early 2021, a rancher filed a lawsuit at the US District Court in  Nevada seeking to block Lithium Nevada’s construction of an open pit lithium mine in the Nevada desert. This suit, as well as others brought by environmentalists and Native American tribes, were consolidated into one at the US District Court.

The Interior Department’s Bureau of Land Management’s approved the company’s plan for the mine in January 2021 during the final days of the Trump Administration. In early February 2023, US District Judge Mirando Du ruled that the Department’s approval of Lithium Nevada’s plan for the mine conformed with federal law. The opponents argued the project should not be allowed per an 1872 law and 2022 ruling out of the 9th Circuit allowing mining of valuable metals to occur on federal land, but not other mining-associated practices like the disposal of rocks.  Judge Du balanced the immediate environmental harms with the longer-term climate impacts, finding the latter took precedence. However, the Judge also asked the Bureau of Land Management whether Lithium Nevada has the right to dispose of mine waste on 1,300 acres of nearby land.

In February 2023, three Native American tribes filed an emergency motion at the 9th Circuit Court of Appeals to prevent the mining project from moving forward. They argued the Bureau of Land Management withheld critical information from the Nevada State Historic Preservation Office and misrepresented the extent to which it consulted local tribes about the project. Additionally, the tribes asserted the Bureau violated the Federal Land Policy Management Act, the National Historic Preservation Act, and the National Environmental Policy Act. The Court denied this request, and the mine’s construction began in early March 2023. The Court did not explain why it rejected the emergency injunction.

Lithium mine wins appeal; construction underway, 5 March 2023, Nevada Appeal

Three tribes file new lawsuit challenging Thacker Pass lithium mine, 21 February 2023, Nevada Current

Thacker Pass lithium mine clears most legal challenges, minus a judge ordered waste rock review, 7 February 2023, Nevada Current

Chronologie

Informations sur la confidentialité

Ce site utilise des cookies et d'autres technologies de stockage web. Vous pouvez définir vos choix en matière de confidentialité ci-dessous. Les changements prendront effet immédiatement.

Pour plus d'informations sur notre utilisation du stockage web, veuillez vous référer à notre Politique en matière d'utilisation des données et de cookies

Strictly necessary storage

ON
OFF

Necessary storage enables core site functionality. This site cannot function without it, so it can only be disabled by changing settings in your browser.

Cookie analytique

ON
OFF

Lorsque vous accédez à notre site Web, nous utilisons Google Analytics pour collecter des informations sur votre visite. Autoriser ce cookie nous permettra de comprendre en plus de détails sur votre parcours et d'améliorer la façon dont nous diffusons les informations. Toutes les informations analytiques sont anonymes et nous ne les utilisons pas pour vous identifier. Outre la possibilité que vous avez de refuser des cookies, vous pouvez installer le module pour la désactivation de Google Analytics.

Cookies promotionels

ON
OFF

Nous partageons des nouvelles et des mises à jour sur les entreprises et les droits de l'homme via des plateformes tierces, y compris les médias sociaux et les moteurs de recherche. Ces cookies nous aident à comprendre les performances de ces items.

Vos choix en matière de confidentialité pour ce site

Ce site utilise des cookies et d'autres technologies de stockage web pour améliorer votre expérience au-delà des fonctionnalités de base nécessaires.