abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb

Esta página não está disponível em Português e está sendo exibida em English

Artigo

25 Mar 2019

Author:
OECD Watch

Korean workers & NGOs file OECD Guidelines complaint against Samsung, Total, Technip & Equinor related to deaths of 6 workers & injury to hundreds more during oil platform construction accident

"KNTC Watch et al vs. Samsung Heavy Industries et al", 20 March 2019

On March 20, 2019... the Samsung Heavy Industries Martin Linge Project Crane Accident Workers Support Team (Worker Support Team) and Korean Transnational Corporations Watch... filed a specific instance against SAMSUNG Heavy Industries (SHI), TOTAL, TECHNIP, and EQUINOR at the Korean, French, and Norwegian National Contact Points. 

On May 1, 2017, during construction of a Martin Linge oil platform at the Samsung Heavy Industries shipyard in South Korea, a Goliath crane and Jib tower crane collided... [T]he accident killed six workers and injured 25 others... 300 workers witnessed the accident, but have not received treatment for the trauma they have suffered. 

According to the complainants, an investigation agency found that just before the accident, SHI had adopted an unusual and dangerous work method without first undertaking a risk assessment... Complainants assert that TECHNIP, leader of the project consortium and recipient of the construction contract, directly supervised the engineering procedures and failed to advise or order appropriate safety management measures, even though the change of construction method was unusual and dangerous. Complainants argue that TOTAL, which operated the project at the time of the incident, did not ensure proper safety assessments were undertaken, while Equinor, the current operator, declined to disclose the investigation report undertaken by the project group after the accident, which might reveal more information about the accident’s cause. 

The NGOs are seeking mediation by the NCPs to help determine the breaches of the Guidelines that have occurred and to assist in their remediation. 

Linha do tempo

Privacy information

Este site usa cookies e outras tecnologias de armazenamento na web. Você pode definir suas opções de privacidade abaixo. As alterações entrarão em vigor imediatamente.

Para obter mais informações sobre nosso uso de armazenamento na web, consulte nossa Política de Uso de Dados e de Cookies

Strictly necessary storage

ON
OFF

Necessary storage enables core site functionality. This site cannot function without it, so it can only be disabled by changing settings in your browser.

Cookies analíticos

ON
OFF

Quando você acessa nosso site, usamos o Google Analytics para coletar informações sobre sua visita. A aceitação deste cookie nos permitirá entender mais detalhes sobre sua viagem, e melhorar a forma como nós colocamos as informações na superfície. Todas as informações analíticas são anônimas e não as utilizamos para identificá-lo. O Google fornece uma opção de não inclusão no Google Analytics para todos os navegadores populares.

Cookies promocionais

ON
OFF

Compartilhamos notícias e atualizações sobre empresas e direitos humanos através de plataformas de terceiros, incluindo mídias sociais e mecanismos de busca. Estes cookies nos ajudam a entender o desempenho destas promoções.

Suas escolhas de privacidade para este site

Este site usa cookies e outras tecnologias de armazenamento da web para aprimorar sua experiência além da funcionalidade básica necessária.