abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb

Bu sayfa Türkçe dilinde mevcut değildir ve şu an English dilinde görüntülenmektedir

Makale

16 Oca 2023

Yazan:
The Independent (Uganda)

East African crude oil pipeline delayed by grievances by project-affected persons

"EACOP construction starts after June, delayed by PAP grievances"

The East African Crude Oil Pipeline (EACOP) company hopes to start construction works in the second quarter of this year when the compensation and resettlement exercise is expected to end. This will be almost a year since the company applied for the construction license from the government in July last year.

The process was delayed by the complexities in settling the Project Affected Persons, PAPs. Honey Malinga, the Ag. the Director of Petroleum in the Ministry of Energy and Mineral Development, says that the application would be processed within 180 days “in accordance with the law.” He has urged the company to pay attention and quickly address the persistent concerns raised by the communities, local leadership, government, and civil society. These issues, which include the valuation of the land, and protection of cultural sites, among others, have persisted beyond the 180 days, thus delaying the project, according to Martin Tiffen, the Managing Director at EACOP.

He, however, says that three-quarters of the PAPs have already signed agreements and are being compensated, while the other processes are ongoing including the procurement of contractors.

Zaman çizelgesi