abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeblueskyburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfilterflaggenderglobeglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalitywebwhatsappxIcons / Social / YouTube

这页面没有简体中文版本,现以English显示

报告

2019年7月8日

作者:
National Environmental Tribunal (Kenya)

National Environmental Tribunal's judgment

"SaveLamu & ors v. NEMA & Amu Power Company Limited"

Accordingly, for the reasons stated above, we allow the appeal and set aside the decision of the 1st Respondent to issue the Environmental Impact Assessment Licence No. NEMA/ESIA /PSL/3798 dated 7th September 2016 to the 2nd Respondent. In furtherance of our powers under section 129(3) (b) and (c) we order the 2nd Respondent, should it still wish to pursue the construction and operation of the project, to undertake a fresh EIA study following the terms of reference already formulated in January 2016, and in compliance with the Director - general's directive of 26th October 2015, as well as adhere to each step of the requirements of the EIA Regulations on EIA Studies. The fresh EIA study, if undertaken, is to, inter alia, include all approved and legible detailed architectural and engineering plans for the plant and its ancillary facilities (such as the coal storage and handling facility and the ash pit with its location in relation to the sea shore), consideration of the Climate Change Act 2016, the Energy Act 2019 and the Natural Resources (Classes of Transactions subject to Ratification) Act 2016 in so far as the project will utilise sea water for the plant and/ or if applicable.

Subject to these steps being undertaken, a fresh EIA study report is to be prepared and presented to the 1st Respondent. The 1st Respondent is directed to comply with the provisions of regulations 17 and 21, engage with the lead agencies and the public, in the manner and strict timelines provided for under the said law. The 1st Respondent is to share its memorandum of reasons for reaching its decision whether for or against the project with the relevant parties and publish its decision on the grant or refusal to issue an EIA Licence accompanied with a summary of its reasons within 7 days of its decision. Such publication should be in a newspaper with nationwide circulation. These extraordinary measures are necessary to ensure sufficient access to information by the public on a project that will be the first of its kind in Kenya and the East African region.

隐私资讯

本网站使用 cookie 和其他网络存储技术。您可以在下方设置您的隐私选项。您所作的更改将立即生效。

有关我们使用网络存储的更多信息,请参阅我们的 数据使用和 Cookie 政策

Strictly necessary storage

ON
OFF

Necessary storage enables core site functionality. This site cannot function without it, so it can only be disabled by changing settings in your browser.

分析 cookie

ON
OFF

您浏览本网页时我们将以Google Analytics收集信息。接受此cookie将有助我们理解您的浏览资讯,并协助我们改善呈现资讯的方法。所有分析资讯都以匿名方式收集,我们并不能用相关资讯得到您的个人信息。谷歌在所有主要浏览器中都提供退出Google Analytics的添加应用程式。

市场营销cookies

ON
OFF

我们从第三方网站获得企业责任资讯,当中包括社交媒体和搜寻引擎。这些cookie协助我们理解相关浏览数据。

您在此网站上的隐私选项

本网站使用cookie和其他网络存储技术来增强您在必要核心功能之外的体验。