abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb

这页面没有简体中文版本,现以English显示

文章

2023年1月20日

作者:
Ryan Dube and Gabriele Steinhauser, The Wall Street Journal

WSJ report exposes serious construction defects and potential corruption in multiple mega infrastructure projects funded and built by China

Shutterstock

China’s Global Mega-Projects Are Falling Apart, 20 Jan 2023

[...T]housands of cracks have emerged in the $2.7 billion Coca Codo Sinclair hydroelectric plant, government engineers said, raising concerns that Ecuador’s biggest source of power could break down. At the same time, the Coca River’s mountainous slopes are eroding, threatening to damage the dam. [...]

China’s Embassy in Ecuador didn’t respond to requests for comment on the hydroelectric project. In a recent letter published on the embassy’s Twitter account in response to a report by the Foundation for Citizenship and Development, the local chapter of anticorruption watchdog Transparency International, on China’s lending practices in Ecuador, the embassy said Chinese loans and projects provided “tangible benefits” to Ecuador at a time when the country was in urgent need of financing. [...]

Flaws in some of the Chinese-built projects have come to light.

In Pakistan, officials shut down the Neelum-Jhelum hydroelectric plant last year after detecting cracks in a tunnel that transports water through a mountain to drive a turbine. [...] [It] was concerned the tunnel could collapse just four years after the 969-megawatt plant became operational. [...]

Uganda's power generation company said it has identified more than 500 construction defects in a Chinese-built 183-megawatt hydropower plant on the Nile river that has suffered frequent breakdowns since it went into operation in 2019. China International Water & Electric Corp., which led construction of the Isimba Hydro Power Plant, failed to build a floating boom to protect the dam from water weeds and other debris, which has led to clogged turbines and power outages, according to the Uganda Electricity Generation Co., or UEGC. [...]

Completion of another Chinese-built hydropower plant further down the Nile, the 600-megawatt Karuma Hydro Power Project, is three years behind schedule, a delay that Ugandan officials have blamed on various construction defects, including cracked walls. UEGC also said the Chinese contractor, Sinohydro Corp., installed faulty cables, switches and a fire extinguishing system that need to be replaced.

Sinohydro and China International Water didn’t respond to requests for comment on the Ugandan projects.

In Angola, 10 years after the first tenants moved into Kilamba Kiaxi, a vast social housing project outside the capital of Luanda, many locals are complaining about cracked walls, moldy ceilings and poor construction. [...] The project, built by China’s CITIC Group, was initially funded through a $2.5 billion, oil-backed credit line from the Industrial and Commercial Bank of China that was later refinanced by the China Development Bank [...].

A spokeswoman for CITIC said humidity issues in a small number of units in Kilamba were due to tenants making improper renovations and that the company had completed required maintenance. [...]

Ecuadorean lawmakers, former government ministers and anticorruption activists say the loans lacked transparency, with contracts given to companies without public bids, resulting in shoddy construction, high costs and graft.

[T]he China Development Bank agreed to finance 85% of Coca Codo Sinclair's initial cost, with a 6.9% interest rate.

The China Development Bank and Sinohydro didn’t respond to requests for comment.

In September, prosecutors searched the office of Sinohydro over allegations it paid bribes to people close to Mr. Correa's vice president, Lenin Moreno, when the contract was awarded to the Chinese firm.

Some engineers questioned the project early on, saying that the environmental studies were out of date.

Since the 2016 opening, officials from the state electricity utility have found more than 17,000 cracks in the power plant's eight turbines, according to the state utility. [...] It blames the fissures on faulty steel imported from China. In 2021, the utility took Sinohydro to international arbitration in Chile, which is ongoing, over demands to repair the damage. [...] Numerous attempts to fix the cracks have failed, utility officials said.

[I]n 2020, the Coca River’s slopes began collapsing, creating thunderous crashes and rattling the ground like an earthquake. The erosion destroyed Ecuador’s biggest waterfall. It took out a stretch of a key road and oil pipeline. The Pink House, a brothel in San Luis that locals say was popular with both Chinese and Ecuadorean workers, tumbled into the river. Ms. Carranza said a neighbor’s home went over the cliff. [...] Fearing for her family’s safety in her own home, Ms. Carranza fled San Luis in March [...]