abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb

這頁面沒有繁體中文版本,現以English顯示

報告

2019年7月8日

作者:
National Environmental Tribunal (Kenya)

National Environmental Tribunal's judgment

"SaveLamu & ors v. NEMA & Amu Power Company Limited"

Accordingly, for the reasons stated above, we allow the appeal and set aside the decision of the 1st Respondent to issue the Environmental Impact Assessment Licence No. NEMA/ESIA /PSL/3798 dated 7th September 2016 to the 2nd Respondent. In furtherance of our powers under section 129(3) (b) and (c) we order the 2nd Respondent, should it still wish to pursue the construction and operation of the project, to undertake a fresh EIA study following the terms of reference already formulated in January 2016, and in compliance with the Director - general's directive of 26th October 2015, as well as adhere to each step of the requirements of the EIA Regulations on EIA Studies. The fresh EIA study, if undertaken, is to, inter alia, include all approved and legible detailed architectural and engineering plans for the plant and its ancillary facilities (such as the coal storage and handling facility and the ash pit with its location in relation to the sea shore), consideration of the Climate Change Act 2016, the Energy Act 2019 and the Natural Resources (Classes of Transactions subject to Ratification) Act 2016 in so far as the project will utilise sea water for the plant and/ or if applicable.

Subject to these steps being undertaken, a fresh EIA study report is to be prepared and presented to the 1st Respondent. The 1st Respondent is directed to comply with the provisions of regulations 17 and 21, engage with the lead agencies and the public, in the manner and strict timelines provided for under the said law. The 1st Respondent is to share its memorandum of reasons for reaching its decision whether for or against the project with the relevant parties and publish its decision on the grant or refusal to issue an EIA Licence accompanied with a summary of its reasons within 7 days of its decision. Such publication should be in a newspaper with nationwide circulation. These extraordinary measures are necessary to ensure sufficient access to information by the public on a project that will be the first of its kind in Kenya and the East African region.

隱私資訊

本網站使用 cookie 和其他網絡存儲技術。您可以在下方設置您的隱私選項。您所作的更改將立即生效。

有關我們使用網絡儲存技術的更多資訊,請參閱我們的 數據使用和 Cookie 政策

Strictly necessary storage

ON
OFF

Necessary storage enables core site functionality. This site cannot function without it, so it can only be disabled by changing settings in your browser.

分析cookie

ON
OFF

您瀏覽本網頁時我們將以Google Analytics收集信息。接受此cookie將有助我們理解您的瀏覽資訊,並協助我們改善呈現資訊的方法。所有分析資訊都以匿名方式收集,我們並不能用相關資訊得到您的個人信息。谷歌在所有主要瀏覽器中都提供退出Google Analytics的添加應用程式。

市場營銷cookies

ON
OFF

我們從第三方網站獲得企業責任資訊,當中包括社交媒體和搜尋引擎。這些cookie協助我們理解相關瀏覽數據。

您在此網站上的隱私選項

本網站使用 cookie 和其他網絡儲存技術來增強您在必要核心功能之外的體驗。