abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeblueskyburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfilterflaggenderglobeglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalitywebwhatsappxIcons / Social / YouTube

このページは 日本語 では利用できません。English で表示されています

レポート

2019年7月8日

著者:
National Environmental Tribunal (Kenya)

National Environmental Tribunal's judgment

"SaveLamu & ors v. NEMA & Amu Power Company Limited"

Accordingly, for the reasons stated above, we allow the appeal and set aside the decision of the 1st Respondent to issue the Environmental Impact Assessment Licence No. NEMA/ESIA /PSL/3798 dated 7th September 2016 to the 2nd Respondent. In furtherance of our powers under section 129(3) (b) and (c) we order the 2nd Respondent, should it still wish to pursue the construction and operation of the project, to undertake a fresh EIA study following the terms of reference already formulated in January 2016, and in compliance with the Director - general's directive of 26th October 2015, as well as adhere to each step of the requirements of the EIA Regulations on EIA Studies. The fresh EIA study, if undertaken, is to, inter alia, include all approved and legible detailed architectural and engineering plans for the plant and its ancillary facilities (such as the coal storage and handling facility and the ash pit with its location in relation to the sea shore), consideration of the Climate Change Act 2016, the Energy Act 2019 and the Natural Resources (Classes of Transactions subject to Ratification) Act 2016 in so far as the project will utilise sea water for the plant and/ or if applicable.

Subject to these steps being undertaken, a fresh EIA study report is to be prepared and presented to the 1st Respondent. The 1st Respondent is directed to comply with the provisions of regulations 17 and 21, engage with the lead agencies and the public, in the manner and strict timelines provided for under the said law. The 1st Respondent is to share its memorandum of reasons for reaching its decision whether for or against the project with the relevant parties and publish its decision on the grant or refusal to issue an EIA Licence accompanied with a summary of its reasons within 7 days of its decision. Such publication should be in a newspaper with nationwide circulation. These extraordinary measures are necessary to ensure sufficient access to information by the public on a project that will be the first of its kind in Kenya and the East African region.

プライバシー情報

このサイトでは、クッキーやその他のウェブストレージ技術を使用しています。お客様は、以下の方法でプライバシーに関する選択肢を設定することができます。変更は直ちに反映されます。

ウェブストレージの使用についての詳細は、当社の データ使用およびクッキーに関するポリシーをご覧ください

Strictly necessary storage

ON
OFF

Necessary storage enables core site functionality. This site cannot function without it, so it can only be disabled by changing settings in your browser.

クッキーのアナリティクス

ON
OFF

When you access our website we use Google Analytics to collect information on your visit. Accepting this cookie will allow us to understand more details about your journey, and improve how we surface information. All analytics information is anonymous and we do not use it to identify you. Google provides a Google Analytics opt-out add on for all popular browsers.

Promotional cookies

ON
OFF

We share news and updates on business and human rights through third party platforms, including social media and search engines. These cookies help us to understand the performance of these promotions.

本サイトにおけるお客様のプライバシーに関する選択

このサイトでは、必要なコア機能を超えてお客様の利便性を高めるために、クッキーやその他のウェブストレージ技術を使用しています。